Liquid Labor · Sites, Power & Capital

Data Center Development Intelligence

Research and compilation by (Uwe Jens Cerron) · About the author · Methodology & citation

Find data center projects by state, compare capacity and investment, and check the sources before choosing a site. Snapshot: September 13, 2026.

What are you looking for?

Open a project to see its sources, power details and what still needs checking.

MW describes the recorded project, not power available to a new buyer.

Research watch

Google: reported exploration in Lea County

Unverified report · 2026-09-14 · Excluded from project and MW totals

A forwarded alert says Google is exploring a potential data center in Lea County. Exploration, location, project scope and a decision to build remain unconfirmed.

Evidence and next steps

Forwarded Market News Feed headline supplied by a reader. Original publication or company statement has not been independently located.

Next step: Find the original Google statement or project-specific county filing. Then verify parcel, utility service, water requirements and approvals.

What would invalidate this lead: Retracted or misattributed report, a different location, or a decision not to proceed.

County background materials. County February 26 meeting materials discuss data-center requirements. They do not confirm a Google project.

Send Uwe a source or correction
Updated September 13, 2026. All 86 Epoch AI sites are available in the global source directory; the 75 US sites are reconciled into this register. Read the first four state briefs. Announced campus capacity and estimated current IT capacity are different measures. Neither is a utility service commitment or metered demand. Regional announcement rows may overlap individual sites; do not sum them as unique campuses. Audit log.
Operational Building Announced Proposed Blocked or withdrawn

Project Register

Select a project to see its sources and what still needs checking. Reported investment is not committed debt or equity. Regional records may overlap individual campuses.

StProjectLocationAnnounced MWEstimated IT MWReported investment / scopeStatusEvidence label
Louisiana
AWS: Louisiana campuses

Amazon updated its planned investment to $18B across three campuses on August 18, 2026. No MW inferred from investment.

Recorded source
Caddo and Bossier parishes; ShreveportNot publishedNot published$18B plannedannouncedVER
Louisiana
Applied Digital

Cleco territory. Same operator as Ellendale, North Dakota.

Rapides ParishNot publishedNot published$3.6BbuildingVER
Louisiana
Hut 8: River Bend

592 acres. 15-year lease reported at roughly $7B.

West Feliciana300 MWNot published$10B Phase IbuildingVER
Louisiana
Entergy generation (Meta)

Approved generation serving Hyperion. Docket U-37425.

Richland2,262 MWNot published, buildingVER
Louisiana
Cleco generation

Docket U-38035. Tenant named: Applied Digital.

Rapides756 MWNot published, buildingVER
Louisiana
Entergy: Project Evest (Meta)

Docket U-37882. Seven 754 MW units, three sited in Pointe Coupee, plus 600 MW storage. Tenant named in the filing: Evest LLC, a Meta subsidiary. Related power infrastructure; excluded from data-center announced-capacity totals to avoid treating generation as IT load.

Pointe Coupee / Big Cajun5,300 MWNot published, announcedVER
Georgia
OpenAI: Project Camellia

1,400 acres, four hyperscale buildings.

Effingham County3,200 MWNot published$20–30BannouncedREP
Georgia
Microsoft: Georgia

Within Southern Company's capital plan.

multiple sitesNot publishedNot publishedin $81.2B planbuildingREP
Mississippi
AWS: Mississippi

Statewide commitment scaled up to $25B.

Madison CountyNot publishedNot published$25B / 2 yrsbuildingVER
Mississippi
AWS: Delphi conversion

Former manufacturing plant reused. Brownfield precedent.

Hinds CountyNot publishedNot published$1BbuildingREP
Texas
Matador / HyperGrid (Fermi America)

5,769 acres. Fermi America is an SEC-reporting company; site and service arrangements are disclosed.

Amarillo, Potter County11,000 MWNot publishedNot publishedannouncedREP
Texas
Data City

Site location not published by the operator.

Texas (approx)5,000 MWNot publishedNot publishedannouncedEST
Texas
Delta

Site location not published by the operator.

Texas (approx)4,000 MWNot publishedNot publishedannouncedEST
Texas
Stream / Plug: Graham

66 acres carrying 164 MW of interconnection. The powered-land price comp.

Young County164 MWNot published$50M at closeoperationalREP
Arkansas
AVAIO Digital: Project Leo

760 acres at I-530 and 145th St. Entergy Arkansas contract for 150 MW at opening June 2027, utility plans 420 MW more. Over 500 MW of behind-the-meter gas plus a 75 MW solar array on site. 1 GW at full buildout is about 5 percent of state generating capacity.

Pulaski County, south Little Rock1,000 MWNot published$6B initial, $21B fullbuildingVER
Arkansas
Google: West Memphis

1,000 acres. Entergy Arkansas ramping new solar and battery storage to serve it. Capacity not published.

Crittenden CountyNot publishedNot published$4B through 2027buildingVER
Arkansas
Little Rock Port Authority campus

One of four hyperscale projects the state Commerce Department counts. Operator not published.

Little RockNot publishedNot publishedabout $1BannouncedREP
Arkansas
Conway campus

Entergy held a community meeting on it. Operator not published.

Faulkner CountyNot publishedNot publishedabout $1BannouncedREP
Texas
Pecos County campus

Three filings of $300M each on a single day, August 2026.

Fort StocktonNot publishedNot published$900MbuildingVER
Texas
Haskell County campuses

Two projects. County population near 5,600.

HaskellNot publishedNot published$700MbuildingVER
Texas
Freebird Phase 1

Entered the record April 2026.

Milam CountyNot publishedNot published$470MannouncedVER
Texas
Prime AUS-01

Caldwell County.

LockhartNot publishedNot published$400MannouncedVER
Texas
BT Gateway

Hunt County.

Royse CityNot publishedNot published$384MannouncedVER
Texas
SAT89/90

Medina County. Largest single filing in the Texas set.

CastrovilleNot publishedNot published$765MbuildingVER
Texas
Sharka campus

Ellis County. Five buildings across multiple filings.

MidlothianNot publishedNot published$1.75BbuildingVER
Louisiana
Red River Mill

Closed 2025. Historic on-site power capacity. Rail, gas, water and wastewater in place.

Campti, NatchitochesNot publishedNot publishedNot publishedproposedVER
Louisiana
Dolet Hills

Retired coal station. Interconnection rights repurposed for solar, in service 2027.

DeSoto Parish240 MWNot published240 MW solarbuildingVER
Tennessee
Colossus 2

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
MemphisNot published946 MWNot publishedoperationalEST
Georgia
Microsoft Fairwater Atlanta

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
FayettevilleNot published636 MWNot publishedoperationalEST
Oklahoma
Google Pryor (North)

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
PryorNot published368 MWNot publishedoperationalEST
Ohio
Meta Prometheus

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
New AlbanyNot published562 MWNot publishedoperationalEST
Ohio
Google New Albany

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
New AlbanyNot published453 MWNot publishedoperationalEST
Texas
OpenAI Stargate Abilene

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
Abilene1,200 MW421 MWNot publishedoperationalEST
Wisconsin
Microsoft Fairwater Wisconsin

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
Mount PleasantNot published369 MWNot publishedoperationalEST
Ohio
Google Columbus

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
ColumbusNot published303 MWNot publishedoperationalEST
Arizona
Google Mesa

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
ArizonaNot published183 MWNot publishedoperationalEST
Iowa
Google Council Bluffs (East)

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
Council BluffsNot published237 MWNot publishedoperationalEST
Nebraska
Google Lincoln

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
LincolnNot published141 MWNot publishedoperationalEST
Tennessee
Colossus 1

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
MemphisNot published340 MWNot publishedoperationalEST
Nebraska
Google Omaha

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
OmahaNot published237 MWNot publishedoperationalEST
Texas
CoreWeave Denton TX

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
DentonNot published262 MWNot publishedoperationalEST
Missouri
Google Kansas City East

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
MissouriNot published105 MWNot publishedoperationalEST
Virginia
QTS Richmond 1

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
SandstonNot published238 MWNot publishedoperationalEST
Virginia
Google Bristow

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
BristowNot published238 MWNot publishedoperationalEST
Minnesota
Meta Rosemount

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
MN 55068Not published178 MWNot publishedoperationalEST
Mississippi
Amazon Madison Mega Site

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
Madison Mega Site Nissan Parkway and HNot published284 MWNot publishedoperationalEST
Arizona
Microsoft Goodyear

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
GoodyearNot published202 MWNot publishedoperationalEST
Indiana
Meta Jeffersonville

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
IN 47130Not published178 MWNot publishedoperationalEST
Oregon
Google The Dalles

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
The DallesNot published154 MWNot publishedoperationalEST
Ohio
AWS New Albany

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
13360 Miller Rd NWNot published213 MWNot publishedoperationalEST
Texas
Google Midlothian

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
MidlothianNot published103 MWNot publishedoperationalEST
Virginia
QTS Richmond 2

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
SandstonNot published180 MWNot publishedoperationalEST
Virginia
QTS Richmond 3

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
SandstonNot published144 MWNot publishedoperationalEST
Alabama
Meta Montgomery

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
AL 36105Not published153 MWNot publishedoperationalEST
Idaho
Meta Kuna

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
601 Kuna Mora RdNot published152 MWNot publishedoperationalEST
Texas
Meta Temple

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
TempleNot published152 MWNot publishedoperationalEST
Wyoming
Meta Cheyenne

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
WY 82007Not published152 MWNot publishedoperationalEST
Mississippi
Amazon Ridgeland

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
1626 County Line Road RidgelandNot published228 MWNot publishedoperationalEST
Alabama
Meta Huntsville

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
ToneyNot published146 MW~$1.5BoperationalEST
South Carolina
Meta Aiken

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
SC 29847Not published142 MWNot publishedoperationalEST
Texas
Coreweave Helios

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
AftonNot published132 MWNot publishedoperationalEST
Virginia
Google Arcola

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
SterlingNot published77 MWNot publishedoperationalEST
Iowa
Microsoft Project Osmium

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
CummingNot published190 MWNot publishedoperationalEST
Nevada
Google Storey County

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
NevadaNot published161 MWNot publishedoperationalEST
Utah
Meta Eagle Mountain

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
Eagle MountainNot published133 MWNot publishedoperationalEST
Ohio
Google Lancaster

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
LancasterNot published137 MWNot publishedoperationalEST
Texas
Google Red Oak

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
Red OakNot published77 MWNot publishedoperationalEST
Tennessee
Meta Gallatin

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
GallatinNot published87 MWNot publishedoperationalEST
New Mexico
Meta Los Lunas

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
Los LunasNot published87 MWNot publishedoperationalEST
North Dakota
CoreWeave Ellendale ND

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
EllendaleNot published68 MWNot publishedoperationalEST
Nebraska
Meta Sarpy

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
NE 68059Not published80 MWNot publishedoperationalEST
Virginia
CoreWeave Chester VA

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
ChesterNot published82 MWNot publishedoperationalEST
Pennsylvania
AWS Berwick

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
BerwickNot published108 MWNot publishedoperationalEST
Nebraska
Google Papillion

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
14651-15249 Gold Coast Rd 68138 PapillNot published237 MWNot publishedoperationalEST
North Carolina
CoreWeave Marble NC

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
MarbleNot published65 MWNot publishedoperationalEST
Texas
Microsoft SAT40

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
San AntonioNot published75 MWNot publishedoperationalEST
Virginia
STACK Infrastructure NVA02

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
ManassasNot published85 MWNot publishedoperationalEST
New York
Anthropic Lake Mariner

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
BarkerNot published42 MWNot publishedoperationalEST
Arizona
Stream Phoenix

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
2950 S. Litchfield RoadNot published64 MWNot publishedoperationalEST
Texas
Microsoft SAT14

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
San AntonioNot published47 MWNot publishedoperationalEST
Texas
Vantage TX1

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
San AntonioNot published32 MWNot publishedoperationalEST
Georgia
CoreWeave Dalton 1 & 2

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
GANot published28 MWNot publishedoperationalEST
Georgia
xAI QTS Atlanta

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
AtlantaNot published17.3 MWNot publishedoperationalEST
Texas
Anthropic Barber Lake

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
TexasNot published0 MWNot publishedbuildingEST
New York
Core42 Lake Mariner

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
BarkerNot published58 MWNot publishedoperationalEST
Oklahoma
CoreWeave Muskogee OK

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
OK 74401Not published0 MWNot publishedbuildingEST
Texas
Crusoe Abilene Expansion

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
AbileneNot published0 MWNot publishedbuildingEST
Texas
Goodnight

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
ClaudeNot published0 MWNot publishedbuildingEST
Iowa
Google Cedar Rapids

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
5800 EDGEWOOD RD SW CEDAR RAPIDSNot published0 MWNot publishedbuildingEST
Indiana
Google Fort Wayne

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
Fort WayneNot published0 MWNot publishedbuildingEST
Louisiana
Meta Hyperion

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
Holly Ridge5,000 MW0 MW$50B+buildingEST
Ohio
OpenAI Stargate Lordstown

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
WarrenNot published0 MWNot publishedbuildingEST
Michigan
OpenAI Stargate Michigan

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
MichiganNot published0 MWNot publishedbuildingEST
Texas
OpenAI Stargate Milam

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
TexasNot published0 MWNot publishedbuildingEST
Texas
OpenAI Stargate Shackelford

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
TX 79601Not published0 MWNot publishedbuildingEST
Wisconsin
OpenAI Stargate Wisconsin

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
MichiganNot published0 MWNot publishedbuildingEST
Iowa
QTS Cedar Rapids

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
FairfaxNot published0 MWNot publishedbuildingEST
Utah
QTS Eagle Mountain

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
Eagle MountainNot published0 MWNot publishedbuildingEST
Indiana
Anthropic-Amazon New Carlisle

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
New CarlisleNot published910 MWNot publishedoperationalEST
Oregon
Meta-QTS Hillsboro 2

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
HillsboroNot published180 MWNot publishedoperationalEST
New Jersey
Microsoft-Nebius New Jersey

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
VinelandNot published50 MWNot publishedoperationalEST
Florida
Fort Meade DC Campus

Stonebridge / Bohler Places. Approved unanimously 15 Apr 2026 on a 20 year development agreement, roughly 1,100 to 1,300 acres of former phosphate mine. Two lawsuits filed May 2026 to void it, plus a recall push against three commissioners. Duke Energy Florida. Tenant not disclosed.

Fort Meade, Polk1,200 MWNot published$2.6BannouncedREP
Florida
Project Tango

PBA Holdings, 202 acres at 20125 Southern Blvd, five buildings. DENIED 5 to 1 on 15 Jul 2026 after a twelve hour hearing and 80+ speakers. Sits 900 to 1,200 ft from Saddle View Elementary and 20 miles from Mar-a-Lago, which is why national press covered it. Adjacent to FPL West County Energy Center. Prior approval for 2M+ sq ft of warehouse and data center on the site was not disturbed by the vote.

Loxahatchee, Palm Beach600 MWNot publishedNot publishedblockedVER
Florida
Sentinel Grove Technology Park

Also called Project Jarvis. Roughly 1,218 acres. Land use application voluntarily withdrawn, county records show canceled as of 26 Feb 2026. FPL territory.

Fort Pierce, St. LucieNot publishedNot published$13.5B reportedblockedREP
Florida
Cielo Haines City

Cielo Digital Infrastructure, roughly 74 acres. Stalled. The city states it lacks permitted water capacity for the requested 150,000 gallons per day.

Haines City, Polk300 MWNot publishedNot publishedproposedREP
Florida
Deltona Lecanto site

Roughly 813 acres. Withdrawn one day after commissioners refused to delay the vote past the election.

Lecanto, CitrusNot publishedNot publishedNot publishedblockedREP
Florida
Okee-One

Roughly 9 to 10 MW, linked to Indian River State College. Scrapped April 2026.

Okeechobee County10 MWNot publishedNot publishedblockedREP
Florida
NextNRG Nassau County campus

Roughly 1,600 acres, 200 MW microgrid phased in 50 MW modules. Nassau County adopted a 12 month moratorium on data center permits on 8 Jun 2026.

Nassau County200 MWNot publishedNot publishedproposedREP
Florida
Atlas Compute St. Lucie

Roughly 200 MW contemplated with on-site generation. Early planning, thinly sourced.

St. Lucie County200 MWNot publishedNot publishedproposedEST
Florida
DC BLOX Palm Coast CLS campus

Cable landing station campus, 20+ acres, designed for six cables. Anchor is Google's Sol cable to Santander, Spain. DC BLOX targets operational Q1 2027, TeleGeography lists Sol at 2028. FPL.

Palm Coast, FlaglerNot publishedNot published$70M bldg 1buildingVER
Florida
Equinix MI1, NAP of the Americas

255,513 sq ft at 50 NE 9th St. The primary Latin America interconnection point in the United States. Built above 500 year flood elevation with 30 hour generator autonomy. Equinix does not publish megawatts and every circulating figure is an unsourced aggregator scrape.

Miami, Miami-DadeNot publishedNot publishedNot publishedoperationalVER
Florida
Equinix MI3 / Monet CLS

Carrier neutral colocation that doubles as the cable landing station for Google's Monet. Boca Raton is the busiest landing point in Florida with seven systems including two planned for 2026 and 2027.

Boca Raton, Palm BeachNot publishedNot publishedNot publishedoperationalVER
North Carolina
Rural Hall campus

Rezoning defeated 5 to 2 on 30 Jul 2026.

Forsyth CountyNot publishedNot published$3BblockedVER
Virginia
Dulles Cloud South

Rezoning rejected 8 to 0 in Jul 2026, days after developers retreated from litigation over the separate 1,760 acre Digital Gateway complex in the same county.

Prince William CountyNot publishedNot publishedNot publishedblockedVER
Virginia
PW Digital Gateway

1,760 acres. Developers withdrew from the legal battle in Jul 2026 after years of litigation.

Prince William CountyNot publishedNot publishedNot publishedblockedREP
Georgia
Project Oak

Rezoning denied unanimously, Aug 2026. Would have expanded permitted use on an industrial property off Walt Sanders Road.

Coweta CountyNot publishedNot publishedNot publishedblockedVER
Arizona
La Osa

Board of Supervisors voted 4 to 1 against rezoning, Aug 2026.

Pinal County, near EloyNot publishedNot publishedNot publishedblockedVER
Pennsylvania
Montour County site

County denied the rezoning that would have allowed a data centre.

Montour CountyNot publishedNot publishedNot publishedblockedREP
Mississippi
Amazon: Warren County

Amazon announced a Warren County campus in November 2025. No site MW disclosed in the cited announcement. County-level map pin.

Recorded source
Warren County (approximate)Not publishedNot published$3B+ plannedannouncedVER
Texas
Meta: El Paso

Meta July 2026: campus under construction, 1 GW planned, capacity expected to begin coming online in 2028. Development cost scope includes buildings and long-lived infrastructure. City-level pin.

Recorded source
El Paso (approximate)1,000 MWNot published$14B development costsbuildingVER
Oklahoma
Google: Stillwater

Google identified Stillwater in its April 30, 2026 OG&E agreement. No campus MW inferred from statewide investment or utility agreement. City-level pin; operating status not established by this source.

Recorded source
Stillwater (approximate)Not publishedNot publishedNot publishedannouncedVER
Oklahoma
Google: Muskogee

Google identified Muskogee in its April 30, 2026 OG&E agreement. Distinct from the CoreWeave Muskogee entry. No campus MW inferred. City-level pin; operating status not established by this source.

Recorded source
Muskogee (approximate)Not publishedNot publishedNot publishedannouncedVER
New Mexico
H5: Albuquerque

Existing carrier-hotel campus at 505 Marquette Ave NW. Operator describes 225,000 square feet across two facilities and 25 carriers. Campus entry; do not add the colocation page as a separate project. MW and investment not published in the reviewed page. Map location is approximate, not a surveyed parcel.

Recorded source
Albuquerque, Bernalillo CountyNot publishedNot publishedNot publishedoperationalVER
Montana
Quantica: Big Sky Digital Infrastructure

Developer describes a proposed 5,100-acre campus and 1,100 MW campus plan. Its 7,235 MW generation interconnection request is a different scope and is not IT load or approved firm power. Power mix, permitting, delivery and customer commitments remain diligence items. Developer statements are not independent confirmation. Map location is approximate, not a surveyed parcel.

Recorded source
Near Broadview, Yellowstone County1,100 MWNot publishedNot publishedproposedVER
Montana
Sabey: Butte

NorthWestern Energy identifies a proposed Sabey campus at Montana Connections near Butte. Its February 2026 financial release describes development agreements and ongoing work toward electric service agreements. Do not infer a binding utility service commitment or allocate combined multi-developer MW to this campus. Map location is approximate, not a surveyed parcel.

Recorded source
Montana Connections Business Development Park, Butte-Silver BowNot publishedNot publishedNot publishedproposedVER
Ohio
Vantage: New Albany OH1

June 3, 2025 operator release: $2.25B construction financing for three pre-leased buildings, 192 MW campus plan. Financing is a reported transaction, not an estimate of total project value or equity. Current commissioning remains unverified. Approximate city pin.

Recorded source
New Albany, Franklin/Licking counties192 MWNot published$2.25B construction debtbuildingVER
Idaho
ValorC3: Boise new campus

May 5, 2025 operator announcement describes a new 10 MW facility, its second in Boise, targeting 2027 operation. Current build-to-suit page describes development. Do not confuse with existing 2 MW Emerald Street facility or count future expansion twice. Announced scope; energization and available inventory require confirmation. Map location is approximate, not a surveyed parcel.

Recorded source
Boise, Ada County10 MWNot publishedNot publishedbuildingVER
Oregon
Flexential: Hillsboro 5

Operator publishes 36 MW critical-load UPS design capacity and offers facility tours. Recorded as published design scope, not Epoch estimated current IT demand or available inventory. Hillsboro temporary land-use moratorium excludes applications submitted before it began; project-specific applicability is not established. Map location is approximate, not a surveyed parcel.

Recorded source
Hillsboro, Washington County36 MWNot publishedNot publishedoperationalVER
Oregon
Flexential: Hillsboro 6

Announced new development; current commissioning not verified. Operator publishes 27 MW critical-load UPS design capacity and facility services. Recorded as published design scope, not metered demand or available inventory. City-level approximate pin offset for legibility. Confirm current commissioning phase and any expansion approvals with operator. Map location is approximate, not a surveyed parcel.

Recorded source
Hillsboro, Washington County27 MWNot publishedNot publishedannouncedVER
New Mexico
OpenAI Stargate New Mexico

Epoch AI current IT power estimate; capacity, not metered demand. CSV retrieved 2026-09-13. Zero means no current IT capacity in this snapshot, not a verified operating status.

Recorded source
Location not supplied in Epoch CSVNot published0 MWNot publishedbuildingEST
Explore the project map

Circle size uses estimated IT MW when available, otherwise announced MW. Pins can be approximate. Hover for names and capacity; click a pin for details.

Moratorium watch · Amber-striped states contain a reviewed local restriction, incentive pause or interconnection hold. Whole-state shading flags a restriction with limited scope; it does not mean every project is prohibited. Solid red identifies a statewide permit moratorium, subject to its exceptions. Neutral shading means unreviewed, not unrestricted. Source register · Register updated 2026-09-14. Individual review dates appear below.
Read jurisdiction, scope and exceptions

Oregon · Hillsboro: 120-day pause on applications for new or expanded primary-use data centers and BESS. Earlier applications may continue. Not a statewide construction ban. Official source · Reviewed 2026-09-13

Oregon · Oregon Enterprise Zone program: HB 4084 pauses data-center Enterprise Zone applications statewide. This concerns tax incentives, not a statewide land-use ban. Official source · Reviewed 2026-09-13

New Mexico · Santa Fe County: County announced an 18-month moratorium with a 1 MW threshold. County jurisdiction only; confirm ordinance effective date and exemptions. Does not establish a ban in Albuquerque or statewide. Official source · Reviewed 2026-09-13

Ohio · Cleveland: City pause on review and permits for new or expanded standalone principal-use data centers, scheduled through October 16. Does not apply statewide or establish a restriction in New Albany. Official source · Reviewed 2026-09-13

New York · New York State: Governor announced a statewide pause of up to one year on new hyperscale data-center discretionary environmental permits not already deemed complete, pending statewide standards. Not a closure of operating facilities; permit scope and exceptions matter. Official source · Reviewed 2026-09-13

Idaho · Bannock County: County news index reports a 180-day pause on accepting or processing data-center permits in county jurisdiction, effective July 30. Linked article body is inconsistent; confirm ordinance text and exemptions with county planning. No statewide ban or Boise restriction inferred. Official source · Reviewed 2026-09-13

Texas · ERCOT interconnection process: Data-center projects advancing through ERCOT interconnection must undergo verification and audit before advancement. ERCOT listed Batch Zero verification requests on September 9. This is an interconnection condition, not a blanket Texas construction ban or a closure of operating facilities. Project clearance and release timing require confirmation. Official source · Latest notice register · Reviewed 2026-09-14

Operational Under construction Announced Proposed Blocked or withdrawn Alaska and Hawaii shown as insets
Compare recorded activity by state
Two measures, different scopes. The large figure sums recorded announcements, excluding identified generation projects. Regional aggregates may overlap campus records, so it is not a deduplicated market total. The green figure sums Epoch's estimated current IT capacity for covered sites. These measures cannot be subtracted to calculate a delivery gap. Unknown values remain unknown. Gulf South Focus selects six states.

Share a site or project update

Landowners: share the county/parish, acreage, parcel reference, asking terms and any written utility response. Developers: share requested MW, target service date, approvals and utility milestones. Investors: tell us whether you finance land, construction, facilities or GPU equipment, and what revenue documents you need.

Contributors can get their project details corrected, add a public source and make their site requirements visible to people researching the market. We check supporting documents before marking availability or financing as verified.

Send a site or correction to Uwe on LinkedIn. Please specify what can be published.

Standards We Hold This Page To

We do not call land powered because a transmission line or substation appears nearby. A site reaches that standard only when the serving utility has addressed the exact parcel, the requested load, the point of delivery, the upgrade cost and the service schedule in writing. Proximity is not capacity, and the distinction is the single most common error in this market.

We do not publish fiber status from a map. Broadband coverage data tells you a provider exists. It does not tell you distance to a splice point or whether two entrance paths are physically diverse. We report fiber on a parcel only where a carrier has confirmed it in writing.

We do not treat announced capital as committed capital. Every row on this page separates what was announced from what has been observed operating, and where a capacity figure was never published we say so rather than estimating one.

We do not underwrite a project on discretionary tax abatements. Where a project creates measurable local employment, training or procurement, those commitments should be documented and verified rather than announced at a groundbreaking.

What we have not settled. Whether prepared land clears at the prices it lists at in this corridor, what a utility and an actual buyer will pay for a site at study stage, and which parcels survive wetlands, flood zone and title. Those are open questions and we would rather publish them as open than resolve them with an assumption.

Scope. This tracker covers announced projects and regulatory activity. Controlled sites, owner negotiations, utility correspondence and parcel-level diligence are not published here.

Disclosure of interest

This tracker is written and maintained by Uwe Cerron, who is a land banker and a developer active in Louisiana. That is not incidental to the page. It is the reason the page exists, and it is a conflict you should price in when you read it.

In practice it means two things. Some of the analysis here comes from work done on live transactions rather than from a desk, which is why the questions asked are operational ones. And Liquid Labor and its affiliates may seek to acquire, option, finance or develop property in some of the regions discussed on this page, including regions described here as underserved or early.

This tracker is research. It is not a property listing, a representation of available capacity, investment advice, an offer to sell or a solicitation of an offer to buy any security. Nothing here should be relied on as the basis for a transaction without independent verification, and where a figure is an estimate the page says so and gives its source.

Reach Out

If you own land
Acreage near a substation, a highway or a rail line in Louisiana, Texas, Mississippi, Alabama, Georgia or Arkansas. We are typically buyers of time rather than price. Terms vary by parcel and are set in the agreement itself.
If you work in compute markets
Operators, developers, utilities, index providers and anyone pricing compute or power. We maintain regional datasets that are not published and we trade notes with people who maintain their own. If you track this buildout seriously, we would like to compare readings.
If you need a site
Operators and developers looking for 10 to 200 MW in the Gulf South. Tell us the load, the timeline and whether it is training or inference, and we will tell you honestly whether anything we hold fits.
Uwe Cerron · Liquid Labor
Connect on LinkedIn
Louisiana and the Gulf South
Research reference: power costs, constraints, local rules & historical tables

Reference Metrics

Historical context below: September 3, 2026 snapshot; not refreshed in this import. See the current register and global directory for the September 13 CSV snapshot.

Conversion figures we use across the corridor. Published so they can be argued with. Where a figure is derived rather than observed, it says so.

46,000 to 67,000
Craft-hours per MW
Derived from construction cost per MW, labor share and loaded craft rate. Planning heuristic.
153 to 236
Non-local crew per $B
Observed range across two Louisiana campuses. The 1.5x spread is a function of local labor supply and commute radius.
50 to 150
Permanent jobs per campus
After thousands during construction. The single most misquoted number in this industry.
1.125 kW
Per humanoid, continuous
The embodied load nobody is provisioning for. Compute is the first order of demand, not the last.
+25%
US load growth to 2030
After two flat decades. Data centers are roughly half of it; industry and electrification are the rest.
~97 GW
Entire US nuclear fleet
94 reactors, five decades. The announced campus set is a large fraction of that, in about three years.
3x to 6x
Prepared vs raw land
Listing spread in the Alexandria to Baton Rouge corridor. Whether it clears at those prices is an open question we are testing.
0
Months of warning in a press release
Regulatory records lead announcements by quarters. Every public map of this buildout is compiled from announcements.

The Five Constraints

What is actually stopping projects right now, ranked, with the number that makes each one real. Every figure below is sourced in the line beneath the table. Where a figure is a vendor or trade estimate rather than a regulatory filing, it says so.

#ConstraintThe numberWhy it binds
1Power deliveryWood Mackenzie put generator step-up transformer lead times at roughly 144 weeks, about 2.8 years, in a Q2 2025 survey, within a published range of 80 to 210 weeks. Since 2019 costs are up 45 percent for GSUs, 77 percent for power transformers and 78 to 95 percent for distribution transformers. BLS producer price data independently shows +87 percent from 2019 to July 2026.Neither PJM nor ERCOT says it cannot serve the queue, and we previously wrote that they did. PJM says a capacity shortfall would mean slimmer reserves rather than an inability to serve load. ERCOT says its 474 GW of requests is inflated and that not all requests result in built projects. The constraint is not the queue. It is that equipment arriving in 2029 sits ahead of everything else on the critical path.
2Political goodwillAt least 75 projects worth about $130B blocked or delayed in Q1 2026 alone, described as the largest single quarter on record and roughly matching all of 2025. Opposition groups grew from 396 to 833 between the end of 2025 and March 2026, now spanning 49 states.This moved from background noise to the leading cause of delay inside twelve months. It is also the only constraint on this list that a developer can influence directly, and almost none of them try until it is too late.
3Skilled tradesBLS puts construction average hourly earnings up 4.4 percent year on year to July 2026, and electrical contractors specifically up 7.6 percent. Turner & Townsend reports data center wage premiums of up to 30 percent in constrained markets, which is a consultancy estimate rather than a statistic.Electricians, welders, pipefitters and HVAC technicians, in that order. Rural sites compete with metro projects for the same travelling crews, and the crews go where the per diem is better.
4Crew housingA campus draws thousands of construction workers against 50 to 150 permanent positions. Rural parishes and counties routinely permit fewer housing units in a year than a single project needs beds.The constraint nobody underwrites. When there are no beds, contractors bus crews from 90 minutes out, productivity falls, and the schedule slips without any single line item explaining why. It is also what turns a supportive community into an opposed one.
5WaterMargaret Cook of the Houston Advanced Research Center told New Mexico legislators on 31 Aug 2026 that full build-out would take state data center water use from just over 500 million to 23.6 billion gallons a year. Most of the increase is indirect, consumed cooling the power plants rather than on site.Binding in the arid Southwest and increasingly contested in the Gulf South. Closed loop and air cooled designs move the burden to power rather than removing it, which pushes the problem back to constraint one.

Sources. Transformer lead times and cost escalation: Rabobank, Supply chain constraints are curbing US data center development, and Data Center Knowledge construction coverage, 2026. Grid operator capacity statements: PJM and ERCOT public filings and testimony as reported 2026. Blocked and delayed projects and opposition group counts: Data Center Watch, Q1 2026 report, as covered by Newsweek and TNW, June 2026. Labor cost escalation: CBRE Global Data Center Trends 2026 and Data Center Knowledge. New Mexico water testimony: Source New Mexico, 1 Sept 2026. Permanent job counts and crew housing: our own analysis across Louisiana campuses, method not published. Ranking is our judgment, not a survey result.

Moratoriums and Political Goodwill

$130B
Blocked or delayed, Q1 2026
At least 75 projects. Largest single quarter on record, and roughly equal to all of 2025 in three months.
396 to 833
Opposition groups, Dec 2025 to Mar 2026
More than doubled in one quarter. Now present in 49 states.
300+
State bills filed, early 2026
MultiState counted more than 300 data center related bills across more than 30 states by 20 Feb 2026. These are bills of every kind, tax, water, noise and rate class, not restriction bills. Statewide moratorium proposals specifically: 11 to 12 at the six week mark, 14 by NCSL's June count.
1
Statewide moratorium in force
New York, Executive Order 62, 14 Jul 2026. Holds state DEC discretionary permits in abeyance for facilities of 50 MW or more until a generic environmental impact statement is complete. No fixed expiry. It does not reach local permits. Maine's legislature passed one at 20 MW in April, the first in the nation to do so, and the governor vetoed it on 24 April. The override failed 72 to 65.

The distinction that matters, and the one most commentary gets wrong, is between an enacted moratorium and everything else. One statewide moratorium is in force, New York's, and it came by executive order rather than legislation. No legislature anywhere has successfully enacted one. Texas is a separate case and is not a moratorium. On 3 August 2026 the Governor sent a letter directing PUCT and ERCOT to audit data centers in the interconnection queue before further approvals. It has no independent statutory force and binds only because the agencies chose to comply. Gibson Dunn states plainly that it is not a moratorium on data center development. Its practical effect is real anyway: roughly 300 projects at 75 MW and above are held, ERCOT told the PUCT on 20 August it targets 10 December for the audit report and has conceded it will not finish the related study by April 2027. The 25 to 75 MW tier is not paused, projects under 25 MW are untouched, existing facilities are untouched, and behind-the-meter generation bypasses the queue entirely.

Most of what actually stops a project is still local, a county commission or a city council, and in one case a tribal government. But not all of it, and we had that wrong here until 2 September.

Sources: Data Center Watch Q1 2026 report and briefings; Newsweek and TNW coverage, June 2026; state legislative tracking as reported by Data Center Watch and Coalition United for Transparency, July 2026. Individual state actions are cited in the Regulatory Position table above.

From the Ground

Our own footage, shot from public rights of way. Satellite tells you a building exists. It does not tell you whether the substation is energised, whether the laydown yard is full, how many crew trucks are parked at seven in the morning, or what the road into the site actually looks like. Those are the things that decide whether a parcel nearby is worth anything.

No field media published yet
First capture run is scheduled for the Louisiana and Arkansas corridor. Everything here will be dated and geotagged, and shot from public roads.

What the Numbers Look Like

Three findings from the Epoch cross-reference, charted. Each is our calculation from their published timeline table, not a figure they report.

Median months from first construction record to first observed megawatt, 28.7 for sites started before 2024 against 13.0 for sites started 2024 or later
The build cycle halved. Twenty campuses. 28.7 months median for pre-2024 starts against 13.0 for 2024 onward. The long tail disappeared too, from a 65 month maximum to 27.
Megawatts observed operating at 26 regional campuses, five of them at zero and still under construction
Observed, not announced. 4,795 MW running across 26 campuses in nine states. Five sites, including Meta Hyperion in Richland Parish, are under construction and producing nothing yet.
Months by which the satellite imagery archive precedes the first logged construction entry, for sixteen campuses
The pictures came first. At sixteen sites the imagery archive predates the first construction entry, by 34 months at xAI QTS Atlanta and 32 at Meta Hyperion. The constraint was never availability. It was attention.

Underlying site records and timelines from Epoch AI, ‘AI Data Centers’, epoch.ai, under CC BY 4.0. Charts and the derived month calculations are ours. Google Pryor is excluded from the medians in the first chart because Epoch's earliest entry for it already shows a building operational, so no build period is measurable.

The National Picture

321
Moratoriums tracked, 32 states
261 reported in force as of 1 Sep 2026. Aggregator figure, see the caution below.
NJ 72 · OH 35
Concentration
New Jersey leads with 72, of which 69 are municipal bans. Then Ohio 35, Michigan 35, Georgia 28. Home rule states with many small municipalities produce many separate actions.
1
Statewide, still
New York only. South Dakota is often miscounted as a second: its moratorium bills SB 232 and HB 1301 failed, and what passed was SB 135, barring the state from overriding local bans, plus water and cost allocation duties at 10 MW.
10
Named projects blocked, on this map
Individual campuses denied, withdrawn or scrapped, shown in red. Not moratoriums, actual projects that died.

The pattern in the vote counts is worth more than the totals. Rural Hall, North Carolina, a $3B project, defeated 5 to 2 on 30 July. Dulles Cloud South in Prince William County, Virginia, rejected 8 to 0. Project Oak in Coweta County, Georgia, denied unanimously. La Osa in Pinal County, Arizona, 4 to 1 against. These are not close votes. When a project reaches a board with organised opposition in the room, it usually loses badly rather than narrowly, which suggests the outcome is decided well before the hearing.

Caution on the 321 figure. It comes from commercial moratorium trackers rather than a primary register, and we have not verified the underlying list. Good Jobs First, which does publish methodology, counts 63 or more local moratorium actions with 54 passed, a much smaller number on a stricter definition. Treat 321 as the widest possible count including proposed, expired and municipal actions in home rule states, and 63 as the conservative one. The truth is between them and we are not going to pretend to know where.

Moratorium Register

Every statewide instrument plus every local moratorium, ban and restrictive ordinance we can confirm, starting with the six Gulf Coast corridor states and extending outward. Compiled 2 September, extended 3 September 2026. A fourth status now appears: LITIGATION, where a local government has gone to court to void a citizen petition rather than adopt it or put it to a vote. Three Kansas cities have done this since August. This is the layer that decides whether a parcel is developable, and it moves faster than construction does.

4
Arkansas, in force
4 confirmed actions total, including pending, rescinded and failed.
2
Florida, in force
4 confirmed actions total, including pending, rescinded and failed.
3
Alabama, in force
4 confirmed actions total, including pending, rescinded and failed.
2
Texas, in force
4 confirmed actions total, including pending, rescinded and failed.
1
Louisiana, in force
3 confirmed actions total, including pending, rescinded and failed.
1
Mississippi, in force
1 confirmed action total, including pending, rescinded and failed.
JurisdictionActionAdopted DurationStatusDetail
Edgerton
Kansas · City
City suing to void a citizen petition
high impact data centres
filed Aug 2026pendingLITIGATIONA resident filed a petition on 15 Jul 2026 under the Kansas statute allowing citizens to propose local ordinances. Signatures were collected and verified by the county legal department. Under state law the city must then either adopt the ordinance or put it to a vote. Edgerton instead sued the organisers and a nonprofit in Johnson County District Court, arguing the petition is void and invalid. The city concedes in its own filing that the drive succeeded and that the statute requires it to adopt or vote. Population roughly 2,000.
El Dorado
Kansas · City
City suing to void a citizen petition
large data centres
2026pendingLITIGATIONOne of three Kansas cities challenging resident petitions that would restrict or prohibit large data centres. Organisers cited demands on local electricity and water supply.
Emporia
Kansas · City
City suing to void a citizen petition
large data centres
2026pendingLITIGATIONThird Kansas city to file. The cities argue the petitions are legally invalid.
Statewide
New York · State
Moratorium, executive order
50 MW and above
14 Jul 2026up to 1 yearin forceExecutive Order 62. Holds DEC discretionary environmental permits in abeyance. Projects with permits already deemed complete may proceed. Separately, the legislature passed the Responsible Data Center Development Act in June 2026; the Governor has not signed it and negotiations continue, so the executive order is the instrument actually in force.
Statewide
Maine · State
Moratorium, legislation
20 MW and above
passed 14 Apr 2026to 1 Nov 2027VETOEDFirst state legislature in the nation to pass one. Governor Mills vetoed it on 24 Apr 2026 and the House override failed 72 to 65. She created an advisory council by executive order instead.
Statewide
South Dakota · State
Not a moratorium
10 MW and above
Mar 2026permanentin forceFrequently miscounted as a second statewide moratorium. SB 232 and HB 1301, both one year moratorium bills, failed. What passed was SB 135, which bars the state from overriding local ordinances that limit or ban data centres, and adds water and cost allocation duties.
Indianapolis
Indiana · City and county
Moratorium
new data centre permits
2026to end of 2027in forceMetropolitan Development Commission approved the pause after the City-County Council backed it with all but one vote. Three already approved projects are exempt.
Flint
Michigan · City
Moratorium
all
8 Jun 202612 monthsin forcePassed 7 to 1. Bars acceptance, review or approval of any data centre proposal.
Henry County
Virginia · County
Regulation, not a ban
all
25 Aug 2026permanentin forceOne of the strictest zoning frameworks adopted anywhere. Requires rezoning plus a special use permit, 1,000 ft setbacks, a 50 dBA noise limit and closed loop cooling. The regulate-rather-than-block template, at a much higher bar than St. Charles Parish.
Broomfield
Colorado · City and county
Moratorium
10 MW and above
7 Jul 2026to Dec 2027in forceHalts permits for data centres at 10 MW or more.
Yankton County
South Dakota · County
Moratorium
all
22 Jul 2026not publishedin forceCounty commissioners passed it roughly four months after the state handed local governments explicit authority under SB 135.
Oklahoma City
Oklahoma · City
Moratorium
all
2026not publishedin forceAmended with exemptions. Edmond separately adopted one through year end.
Baltimore
Maryland · City
Moratorium
all
2026not publishedin forceLocal pause reported among the growing set of city level actions.
Independence County
Arkansas · County
Moratorium
all
Aug 2026 (ord. 17 Aug)5 years, to 31 Aug 2029in forceQuorum court, unanimous, with an emergency clause making it effective immediately. The longest data center moratorium adopted anywhere in the corridor.
Union County
Arkansas · County
Moratorium
all
Jun 20261 yearin forceQuorum court.
Carroll County
Arkansas · County
Moratorium
all
Jun 20261 yearin forceQuorum court.
Russellville
Arkansas · City
Moratorium
all
Jul 20266 monthsin forcePause on approving facilities.
Cullman
Alabama · City
Moratorium
all
20261 yearin forceAdopted unanimously.
Fort Payne
Alabama · City
Moratorium
all
16 Jun 20266 monthsexpired or expiringSix month pause.
Anniston
Alabama · City
Moratorium
all
18 Aug 2026not publishedin forceAdopted the same day as Westover.
Westover
Alabama · City
Moratorium
all
18 Aug 2026not publishedin forceAdopted the same day as Anniston.
Jackson
Mississippi · City
Ban
all
14 Jul 2026183 daysin forceFirst in Mississippi. Passed 5 to 2, so under city rules it took effect 30 days later rather than immediately.
Nassau County
Florida · County
Moratorium
data centre, data processing and crypto mining permits
8 Jun 2026up to 12 monthsin forceOrdinance 2026-044, with a fact finding committee. Sits over the proposed NextNRG 1,600 acre campus.
Sarasota County
Florida · County
Moratorium
50 MW and above
9 Jul 20261 year, to Jul 2027in forceAdopted 5 to 0.
Palm Beach County
Florida · County
Moratorium
hyperscale AI
first reading 28 Aug 20261 year proposedpendingSecond and final reading expected late September 2026. Follows the denial of Project Tango in the same county.
Jackson County
Florida · County
Moratorium
not published
noticed 20261 year proposedpendingProposed, not yet adopted.
Austin County
Texas · County
Moratorium
AI data centres and battery storage
Jul 2026not publishedin forceCounty of roughly 30,000 west of Houston. Covers battery energy storage as well as data centres.
San Marcos
Texas · City
Moratorium
all
Jun 2026not publishedin forceFirst Texas city to adopt one.
Fort Worth
Texas · City
Moratorium
all
first step 12 Aug 202690 days proposedpendingCity council voted unanimously to begin the process. Regulation framework being drafted alongside.
Hill County
Texas · County
Moratorium
all
May 2026rescinded ~Jun 2026RESCINDEDFirst moratorium in Texas. Repealed roughly a month later after a developer sued the county for $100M in damages. The only rescission in the corridor and the clearest illustration of the legal exposure.
New Orleans
Louisiana · City
Moratorium
all
introduced 20261 year proposedpendingTemporary moratorium while the city planning commission holds hearings on zoning definitions and land use controls. Adoption status not confirmed.
Caddo Parish
Louisiana · Parish
Moratorium
all, unincorporated commercial and industrial
attempt failed Aug 2026n/aFAILEDCommissioners voted 6 to 4 against even sending it to the planning and zoning commission. The parish attorney advised that a moratorium cannot be enacted by resolution because a resolution has no force of law under the charter, and that a use specific moratorium in an area without a master plan and zoning ordinance conflicts with the Louisiana Constitution of 1974 and Title 33.
St. Charles Parish
Louisiana · Parish
Regulation, not a ban
all
2026permanentin forceCouncil unanimously added a data centre definition to the zoning code with setbacks, landscaping, buffering, equipment screening and noise limits, and a 300 ft buffer from residential districts, schools, day cares, nursing homes, assisted living and parks. The template for regulating rather than blocking.
Arkansas is the most restrictive, and it is not close
Four confirmed local moratoriums including a five year ban in Independence County adopted with an emergency clause. The same state cut energy project review to six months and has four hyperscale projects worth about $12B. Fastest state permitting in the corridor, most aggressive counties. Both are true at once.
Louisiana blocks are failing on legal grounds
Caddo Parish's attempt died 6 to 4 before it even reached planning and zoning. The parish attorney's reasoning is the important part: a resolution has no force of law under the charter, and a use specific moratorium in an area with no master plan or zoning ordinance conflicts with the Louisiana Constitution of 1974 and Title 33. Many Louisiana parishes have no comprehensive zoning, which leaves them with weaker legal tools to block than their neighbours have.
Hill County shows the exposure
Texas's first county moratorium, adopted May 2026, was repealed roughly a month later after a developer sued for $100M in damages. It is the only rescission in the corridor. Any jurisdiction adopting one after that date is doing so with that precedent on the record, which is worth knowing before assuming a moratorium will hold.

Sources. Arkansas: UALR Public Radio, 12 Aug 2026. Mississippi: Mississippi Today and WLBT, 14 Jul 2026. Alabama: local reporting on Cullman, Fort Payne, Anniston and Westover, Jun to Aug 2026. Texas: MultiState case study 19 Aug 2026, Texas Tribune 30 Jun 2026 on San Marcos, Fort Worth Report 12 Aug 2026. Louisiana: KTBS, KSLA and The Center Square on Caddo Parish Aug 2026, Herald-Guide on St. Charles Parish, DCD on New Orleans. Florida: Nassau County ordinance 2026-044, MySuncoast 9 Jul 2026, WFLX 28 Aug 2026.

What this table is not. It is not exhaustive. MultiState reports that Texas municipalities alone have considered at least 100 local data center ordinances since July 2025, and we have confirmed four. Absence from this table means we could not confirm an action, not that none exists. Statewide instruments are covered separately in the Regulatory Position section above, and Texas's interconnection audit is not a moratorium.

Regulatory Position by State

Where each state sits right now on large load, and what changed most recently. Regulatory posture moves faster than construction and it is the variable that decides whether a parcel is developable, so we track it separately from capacity. Dates are the date of the action, not the date we read it.

StatePostureMost recent actionWhat it means for siting
ArkansasOPENLegislature passed a data center incentive in 2023, refined in 2025. Sales and use tax exemption. Energy project permitting cut from 12 to 18 months down to 6 months. The Secretary of Commerce states the state has not recruited any of the four hyperscale projects and that developers work with the utility first.The six month energy permit is the fastest in the corridor. Entergy territory in central and east Arkansas is vertically integrated, which is why projects land there and not in the northwest, where co-ops and SWEPCO create a transmission lag.
GeorgiaSPLITPSC staff approved Georgia Power's 3.2 GW OpenAI contract by letter filed 26 Aug 2026. The Commission took no affirmative public vote and under Georgia's large load process it does not have to. The contract itself is not public. Eleven or more jurisdictions have a moratorium or ban in force, Dougherty County extended 180 days on 31 Aug.Approved at the commission, refused at the county line. Site selection is now a county-by-county question, not a state one.
TennesseeSPLITTVA board created a data center rate class on 20 Aug 2026, described in coverage as one of the first among large US utilities rather than the first in the nation, a capacity commitment charge on new load above 5 MW, effective 1 Oct. Nashville banned any data center over 500,000 sq ft in Davidson County and paused permits through 1 Dec. Knox County and Knoxville paused to June 2027.A utility does not invent a customer class for a handful of projects. Metro is closed, the TVA footprint outside it is being priced rather than blocked.
AlabamaFORMINGPSC opened Docket 33709 on 8 Jul 2026 to govern contracts above 150 MW, ahead of a law effective 1 Oct. The proposed tariff has almost no numbers in it and contains a 45 day deemed approval window. A contract filed 24 Jul is redacted on size and price.Rules are being written now. The 45 day deemed approval means a contract can clear by regulator silence.
New MexicoCONTESTEDState Supreme Court declined to lift its stay on Project Jupiter's air permit hearing on 1 Sep 2026. One analyst, Margaret Cook of the Houston Advanced Research Center, told the interim Water and Natural Resources Committee on 31 Aug 2026 that full build-out would take state data center water use from just over 500 million to 23.6 billion gallons a year, most of it indirect. A statewide moratorium bill is headed to the 2027 session.Water is the binding constraint and it is in front of a court. County commissioners were briefed on 700 MW to 1 GW while air permit filings point to as much as 2.8 GW of on-site generation.
NevadaCONTESTEDNV Energy sued Tract on 24 Jul 2026 in Washoe County District Court. It is not an interconnection cost dispute: NV Energy seeks to stop Tract taking supply obligation questions to private arbitration, arguing they belong to the PUCN. The megawatt figures in the filings are Tract behind-the-meter plants of 144 MW and 218 MW. Henderson rejected a moratorium and used code changes instead, Clark County took no action, Boulder City rejected a project that BLM then approved on federal land.Cost allocation for interconnection is unresolved and now in court. NV Energy's own plan takes data centers from about 5 percent of sales to 64 percent by 2046.
OklahomaSPLITCherokee Nation banned hyperscale data centers on tribal and trust land on 5 Aug 2026 after 64 percent of 1,593 surveyed citizens opposed. It is a Principal Chief policy action binding roughly 67,000 acres of tribal and trust land inside a 4.4 million acre reservation, so two projects continue inside the reservation on non-tribal land. Edmond passed a moratorium through year end, Oklahoma City amended its own with exemptions.The reservation covers Mayes, Muskogee and Tulsa counties, which is where Google is building. First case of a sovereign government reaching a different answer from the state around it.
MississippiOPENOver $56B announced. MDEQ permitted a 41 turbine, 1.2 GW plant for xAI in March 2026 with service by July 2027. The company began removing 69 unpermitted temporary turbines in Aug.Permissive and fast. The air quality fight is cross-border, since Southaven is in Mississippi and the airshed is Memphis.
LouisianaOPENLarge load service continues through LPSC dockets. No state or major parish restriction in force. Meta Hyperion at 5 GW and the Evest filings at 5.3 GW both moved without a moratorium response.Still the most permissive posture in the corridor.
TexasOPENTDLR registers commercial construction at design stage, which makes intent legible earlier here than anywhere else.Fast, but ERCOT large load queue position rather than permitting is the real gate.

Posture is our judgment, not a rating. OPEN means no state or major local restriction currently blocks a large load siting. SPLIT means the state or utility is accommodating while local jurisdictions are refusing. CONTESTED means an unresolved court or commission proceeding could change the answer. FORMING means the governing rules are being written now. This table is reviewed weekly and will be wrong between reviews.

Observed Build, Cross-Referenced Against Epoch AI

Everything above this section is announced capacity. This section is different. These 26 sites are the ones in our nine states plus Arizona that appear in Epoch AI's open database, which is compiled from tasked satellite imagery and permit records rather than from press releases. The megawatt figures are what has been observed operating, not what was announced. We publish both because the gap between them is the whole point.

28.7 months
Land clearing to first MW, pre-2024 starts
Median across 11 sites. Range 20.7 to 64.8 months.
13.0 months
Same measure, 2024 starts onward
Median across 9 sites. Range 3.6 to 26.6. The buildout has compressed by roughly 55 percent.
4,795 MW
Observed operating, 26 sites
Against roughly $182B of estimated capital. Compare this against the announced totals elsewhere on this page.
5
Under construction, zero MW observed
Including Meta Hyperion in Richland Parish, first seen 20 Dec 2024, and Stargate Shackelford, first seen 1 Aug 2025.
SiteStateOwner Observed MWFirst seen Months to first MW
Colossus 2
5420 Tulane Rd, Memphis, TN 38109
TennesseeSpaceXAI
for Anthropic , Cursor , SpaceXAI
9462025-02-288
Microsoft Fairwater Atlanta
1435 Hwy 54 W, Fayetteville, GA 30214
GeorgiaMicrosoft
for OpenAI , Microsoft
6362023-04-0930
OpenAI Stargate Abilene
5502 Spinks Rd, Abilene, TX 79601
TexasOracle
for OpenAI
4212024-05-3116
Google Pryor (North)
4581 Webb St, Pryor, OK 74361
OklahomaGoogle
for Google DeepMind
3682024-07-190
Colossus 1
3231 Riverport Rd, Memphis, TN 38109
TennesseeSpaceXAI
for Anthropic
3402024-04-244
Amazon Madison Mega Site
Amazon Data Services Inc, Madison Mega Site Nissan Par
MississippiAmazon
for Anthropic
2842023-10-0221
CoreWeave Denton TX
8171 Jim Christal Rd, Denton, TX 76207
TexasCoreWeave
for OpenAI
2622024-11-017
Amazon Ridgeland
1626 County Line Road Ridgeland, Mississippi
MississippiAmazon
for Anthropic
2282024-02-2427
Microsoft Goodyear
14250 W Broadway Rd, Goodyear, AZ 85338
ArizonaMicrosoft
for OpenAI , Microsoft
2022021-06-2122
Meta Montgomery
Co Rd 42, Montgomery, AL 36105, USA
AlabamaMeta1532025-03-0116
Meta Temple
2310 Eberhardt Rd, Temple, TX 76504
TexasMeta1522022-04-0144
Meta Huntsville
5400 Prosperity Dr NW, Toney, AL
AlabamaMeta1462021-04-0159
Coreweave Helios
984 County Road 112, Afton, TX 79220
TexasCoreWeave
for OpenAI
1322025-05-3113
Google Midlothian
3250 Railport Parkway, Midlothian, TX 76065
TexasGoogle1032023-11-2829
Meta Gallatin
1 Meta Lp, Gallatin, TN 37066
TennesseeMeta872023-09-1133
Meta Los Lunas
4250 Messenger Lp, Los Lunas, NM 87031
New MexicoMeta872024-07-2419
Google Red Oak
330 Austin Blvd, Red Oak, TX 75154
TexasGoogle772023-04-3028
Microsoft SAT40
15000 Lambda Drive, San Antonio, TX 78245
TexasMicrosoft752018-12-2865
Microsoft SAT14
3545 Wiseman Boulevard, San Antonio, TX 78251
TexasMicrosoft472022-02-1828
Vantage TX1
14720 Omicron Dr, San Antonio, TX 78245
Texasnot identified322023-12-1526
xAI QTS Atlanta
1025 Jefferson Street NW, Atlanta, GA 30318
GeorgiaSpaceXAI172024-01-2313
CoreWeave Muskogee OK
1525 W 43rd St S, Muskogee, OK 74401, USA
OklahomaCoreWeave
for OpenAI
0, building2024-11-18not yet
Crusoe Abilene Expansion
5502 Spinks Rd, Abilene, TX 79601
TexasMicrosoft0, building2025-11-02not yet
Goodnight
10001 Lima Rd, Claude, TX 79019
TexasGoogle SPEC
for Google DeepMind
0, building2025-05-19not yet
Meta Hyperion
Holly Ridge, LA 71269
LouisianaMeta0, building2024-12-20not yet
OpenAI Stargate Shackelford
175 Private Road 1604, Abilene, TX 79601, Shackelford
TexasOracle
for OpenAI
0, building2025-08-01not yet

Site records, addresses, ownership, observed power and construction timelines from Epoch AI, ‘AI Data Centers’. Published online at epoch.ai. Retrieved from https://epoch.ai/data/ai-data-centers [online resource]. Database version 1 September 2026, used under the Creative Commons Attribution 4.0 licence. Months to first megawatt, the pre-2024 and post-2024 split, and the regional subset are our calculations from their timeline table. Epoch estimates their coverage at about 46 percent of global deployed AI compute with a 90 percent interval of 26 to 79 percent, and reports 80 percent of their power estimates fall within 1.4 times the true value. Their inclusion rule is that a planned site enters the database only once construction has started, so absence from this table is not evidence that nothing is planned. Owner and user attributions are Epoch's, carrying their own confidence tags.

Industrial Power Cost by State

The first question every counterparty asks, and the one most often answered from memory. These are the average industrial retail prices reported to the Energy Information Administration on forms EIA-861, for calendar year 2024, the most recent complete state-level series. Read the caveats below before quoting any of them.

5.61¢
Louisiana industrial average
31 percent below the national average of 8.13 cents. Only New Mexico is cheaper among the states on this page.
6.05¢
West South Central region
Texas, Louisiana, Oklahoma and Arkansas together. The cheapest industrial power region in the country.
8.13¢
US industrial average
Across 1.1 million industrial customers. The relevant benchmark for a siting conversation.
1.9×
New Mexico to Nevada spread
5.43 against 8.64 cents. At 100 MW running continuously that difference is roughly $28M a year.
StateCents per kWhvs US averageProjects tracked
New Mexico5.43-2.701
Louisiana5.61-2.5210
Oklahoma5.84-2.292
Texas6.12-2.0126
Tennessee6.21-1.923
Arkansas6.61-1.524
Iowa6.80-1.334
Mississippi6.81-1.324
Ohio7.10-1.036
Georgia7.21-0.924
Alabama7.25-0.884
Nebraska7.66-0.474
Arizona7.90-0.233
Indiana8.15+0.023
Wisconsin8.54+0.411
Nevada8.64+0.511
Virginia8.99+0.867

Three caveats, and they matter. These are averages across all industrial customers in a state, not large-load tariff rates. A campus at 100 MW or above negotiates a dedicated contract and will typically land below the state average, sometimes well below, with terms that are frequently redacted. Second, this is 2024 data, the most recent complete EIA-861 series, and retail prices have risen since across most of the country, so treat these as relative ranking rather than a current quote. Third, the state average tells you nothing about the delivered cost at a specific bus, which is where interconnection cost allocation, special facilities charges and any behind-the-meter generation actually decide the number.

Source: US Energy Information Administration, forms EIA-861 schedules 4A-D, EIA-861S and EIA-861U, 2024 average monthly bill, industrial sector, table 5c.

Connectivity, the Criterion Nobody Publishes

Corrected 2 September 2026. An earlier version of this section said no program in these states requires fiber, sets a distance threshold or specifies bandwidth. That was wrong on three counts and we have rewritten it. Louisiana's application does ask whether fiber is currently available and for the distance to the nearest telecommunications line and central office. Oklahoma's Site Ready standard specifies a T-3 line minimum with fiber preferred. Tennessee requires a provider letter stating the type of service available. Texas has no statewide certification program at all.

What does survive, and it is the part that matters: not one of these programs requires fiber redundancy or physical route diversity, even though several of them explicitly require dual electric feeds and dual water sourcing. Electricity has to be redundant. Fiber does not.

ProgramSitesElectric criterionTelecom criterion
Louisiana LED Certified Sites125+Megawatts, redundancy specifiedAsks whether fiber is available, plus distance to nearest line and central office. No redundancy requirement.
Georgia GRAD and GRAD-Select70+MegawattsDocumented in the site profile. No redundancy requirement.
Select Tennessee Certified Sites64 active, 77 certified to dateMegawatts, dual feed addressedProvider letter stating type of service available. No redundancy requirement.
Alabama AdvantageSite59MegawattsDocumentation of location, extent and quality of service.
NNDA Certified Sites (a five county regional authority, not a Nevada statewide program)10MegawattsTelecommunications run to the property. No redundancy requirement.
TVA and Quest Mega Site standardNot listed30 MW within 18 months, redundant service required, preferably two substationsFiber within 18 months. No redundancy language at all. The clearest example of the asymmetry.
Mississippi MDA Site DevelopmentNot listedMegawattsAn eligible expenditure, not a criterion.
Oklahoma Site ReadyNot listedMegawattsSpecifies bandwidth: T-3 line minimum, fiber optic preferred. No redundancy requirement.
TexasNot listedNot listedNo statewide site certification program exists.
New MexicoNot listedMegawattsNo published telecom criterion found.

So how do you actually find out whether a specific site has fiber, and what kind? You cannot read it off any public listing. Here is the honest hierarchy, cheapest first.

StepCost and timeWhat it tells you, and what it does not
1. NTIA National Broadband Map and FCC Broadband Data CollectionFree, 30 minutesWhich providers serve the address. Tells you a provider exists. Tells you nothing about route diversity, capacity, or distance to a splice point. A screen, not an answer.
2. Read the corridorFreeLong haul fiber follows Class I railroad, interstate and pipeline rights of way. A parcel adjacent to I-10, I-20, I-40 or I-49 very likely has long haul in the ROW. But fiber in the ROW is not fiber you can use. You need a splice point and a carrier willing to open the sheath, and that gap is where most sites die.
3. Carrier building qualificationFree to ask, 4 to 8 weeksThe only step that gives a real answer. Call the wholesale or fiber sales desk with lat, long and parcel ID and request a building qualification or special construction quote. Ask five things: distance to nearest lit fiber and nearest splice point; whether conduit exists to the property line and who owns it; whether they can deliver two entrances on physically diverse routes to different POPs; the special construction estimate and interval; and whether they will share the route KMZ under NDA.
4. Verify the diversity claimFreeCarriers will sell you “diverse” that shares a manhole. Get the route KMZ from both carriers and overlay them. If the routes touch anywhere, including a shared bridge or river crossing, it is not diverse.

Carriers worth calling across this corridor: Lumen, AT&T, Zayo, Uniti, Conterra, Segra, Crown Castle Fiber, FiberLight, Cogent and Arelion, plus Cox Business and, near Lafayette, LUS Fiber. You want at least two that can each deliver independently. Budget for the lateral: rural underground builds commonly run into the high tens of thousands of dollars per mile and considerably more with bores or a water crossing, so a splice point twelve miles away with a river in between is a real number that belongs in your land price.

We publish fiber status per parcel only where a carrier has confirmed it in writing. Anything else is a guess, and a guess about route diversity is the kind that ends a tenant conversation.

68.1%
Speed of light in fiber
Group index 1.4682 at 1550 nm, from the Corning SMF-28 Ultra spec sheet. Roughly 4.9 microseconds per kilometre. Distance to a point of presence is a physical property of a parcel, not a negotiable one.
2 paths, not 2 bills
What diversity means
Two conduits, two rights of way, two points of presence, converging nowhere. Two carriers renting strands in the same duct is one path with two invoices.
17M → 47M
Lumen intercity fiber miles
End of 2025 to the end of 2028 target, against roughly $13B of private connectivity agreements. The long haul network is being rebuilt now, and where it lands decides which rural counties are viable.

We also read roughly twenty of the largest project announcements across these states. None cite fiber as a reason for choosing the site. That is not because it does not matter. Fiber is a disqualifier rather than a differentiator, and nobody publishes the reason they were not rejected.

What the Other Public Sources Cover

Use these sources to check project announcements, utility requests and permits. Each covers a different part of the development process.

SourceStrengthWhere the record starts, and stops
Epoch AI, Data on AI Data Centers86 sites, 13.3 GW, built from tasked satellite imagery and permit records. Open licence. Publishes its own error rates, which almost nothing else does.By their stated rule a site enters only once construction has started. The first timeline entry for Meta Richland Parish, Stargate Abilene, Stargate Shackelford and the Amazon Madison mega site is the phrase "land clearing begins." No acreage, no parcel, no ownership, no fiber. Water populated on 16% of rows, the utility relationship on 21%.
Utility interconnection queuesThe earliest reliable signal. A large load service application at a named point of interconnection leads dirt by 12 to 36 months.Fragmented across ERCOT, MISO, SPP and individual utilities. No common schema, and load-side visibility is far worse than generation-side.
State construction and air permitsFiled at design stage, before announcement. Owner may be withheld, county and cost are not.Every state runs a different system. Some publish nothing.
Company announcementsNames, dollars, and a date.Published after the land is bought and the incentives are signed. Zero months of warning.

To assess a parcel, connect the utility response with ownership, zoning, mineral rights, wetlands and water availability. Some records are public; others require confirmation from the owner or utility.

How We Classify

Each entry labels its sources. Announced capacity and estimated IT capacity appear in separate columns.

TierDefinitionWhat it should be used for
VERRead from a primary source: a regulatory filing, a utility docket, a state record or a company filing.Read the source, then confirm the parcel and utility terms before committing money.
REPReported by a named outlet and not independently confirmed against a primary source.Find the original filing or announcement before relying on the claim.
ESTCompiled from announcements or third-party aggregation. Claimed, not measured.Compare estimates using the source’s method and uncertainty range.

Data Access

The full project register is published as machine readable JSON so it can be cited, audited and re-analysed without scraping this page.

/tracker/projects.json  130 records. Fields: name, state, location, announced_gw, observed_gw, capital, status, confidence, note, source.

Published under CC BY 4.0. Attribute as: Liquid Labor, ‘Reindustrialization Tracker’, liquid-labor.com/tracker/, retrieved [date]. Records derived from Epoch AI are themselves CC BY 4.0 and carry that attribution in the source field. Keep announced capacity and estimated current IT capacity separate when reusing the data.

Sources and Method

Project entries identify their sources where available. Calculations and third-party estimates are labeled; missing figures remain blank or marked as not published.

SourceLicenceWhat we take from it
Epoch AI, ‘AI Data Centers’
epoch.ai/data/ai-data-centers, version 1 Sept 2026
CC BY 4.0 Site records, addresses, coordinates, ownership and tenancy with their confidence tags, observed power, and construction timelines for the 26 regional campuses. Epoch estimates coverage at about 46 percent of global deployed AI compute with a 90 percent interval of 26 to 79 percent, and reports 80 percent of power estimates fall within 1.4 times the true value. We carry those error bars forward rather than presenting their figures as measurements. The months-to-first-megawatt calculations and the pre-2024 against post-2024 split are ours.
State utility commissions
LPSC, Georgia PSC, Alabama PSC, TVA board
Public record Large load dockets, tariff proceedings, rate class decisions and contract filings. Primary source, cited by docket number where one exists.
State construction and environmental permitsPublic record Design-stage filings and air permits. Owner may be withheld; county, cost, work type and date are not.
Data Center Watch
datacenterwatch.org, Q1 2026 report
Cited, not reproduced Blocked and delayed project totals, opposition group counts, state bill tracking.
CBRE, Rabobank, Data Center KnowledgeCited, not reproduced Equipment lead times, cost escalation and labour figures in The Five Constraints. Trade and analyst estimates, not filings, and labelled as such.
Named news reportingCited, not reproduced Individual state actions in the Regulatory Position table, each with an outlet and a date.
Our own field captureOurs Photography and video in From the Ground, shot from public rights of way, dated and geotagged.

Announced spending does not tell you how much financing has closed. Epoch capacity figures are estimates, not measurements. Check the source date and scope before comparing projects.

Corrections. Found an error? Send the project name, the correction and a dated source.

Definitions

Announced capacity. The capacity stated in a project announcement. Check the utility agreement and construction schedule to see how much is committed and when it can be delivered.

Energized capacity. Power actually deliverable at the meter under an executed service agreement. Confirm the available load and operating conditions with the utility.

Open window. A generation or large-load proceeding with no tenant named. Check tenant commitments and comparable land sales before assuming nearby acreage has increased in value.

Stranded interconnection. Grid capacity built for a facility that has since closed or retired. Confirm that the connection rights remain valid, can transfer and can serve the proposed load.

Basis. What the land cost before anyone knew what it was near. Basis discipline is the difference between a durable position and a bet on a press release.

The jobs cliff. Thousands of construction workers for three to five years, then fifty to a hundred and fifty permanently. Every county negotiating right now is negotiating around this number whether or not anyone has said it out loud.

Confidence. VER primary source, filing or docket. REP reported by a named outlet, not independently confirmed. EST from the AI-compiled 13-campus map published 1 Sept 2026 under a paid partnership. Claimed, not measured.

Sources. Meta Hyperion acreage, 1.4 GW target and the $3.3B Louisiana tax package from state and company announcements. AWS $12B Louisiana and $25B Mississippi, and the Hinds County Delphi conversion, from Data Center Dynamics. OpenAI Project Camellia, Effingham County, 3.2 GW on 1,400 acres, $20-30B, reported. Southern Company $81.2B capital plan across Alabama and Georgia, reported. Louisiana dockets U-37425, U-38035 and U-37882 read directly from LPSC filings. Stream / Plug Power Young County terms from Data Center Dynamics. Geography rendered from the us-atlas TopoJSON, projected to Albers USA and embedded as static paths.

Coordinates are parish, county or metro centroids, never parcel locations. Where an operator has not published a site location, the pin reflects a regional placement and the project is flagged accordingly in the register.
This page is informational only. It is not an offer to sell or a solicitation of an offer to buy any security, and it is not investment advice. Figures are compiled from public records and public reporting and are stated as of the date shown.
LIQUID LABOR