Arkansas · State / regional scopeUnreviewedArkansas Public Service Commission
acility at a single metered location shall have: (1) A minimum peak electrical demand of greater than one megawatt (1 MW) at that location based upon the prior twelve (12) months’ billing history at the time of the application; or (2) An annual natural gas consumption of greater than seventy thousand million British thermal units (70,00
Filing date: Not normalized. Collection: 2026-09-13T22:40:26.673143+00:00.
Tennessee · Shelby CountyUnreviewedMemphis Light, Gas and Water
y metered and billed, except MLG W may direct that more than one set of service conductors be installed for large loads in the underground network areas. Separate primary circuits of the same voltage, terminating in a common switch room or vault, adjacent bays of a structure or adjacent p ad-mount metering units may be totalized. In these cas
Filing date: Not normalized. Collection: 2026-09-13T22:40:29.650827+00:00.
Tennessee · Shelby CountyUnreviewedMemphis Light, Gas and Water
t of $1,104,000.00. (Randy Orsby) (REOUIRES CITY COUNCIL APPROVAL) 4. Resolution awarding Contract No. 12688, Substation Engineering Design to RMS Energy Co., LLC in the funded amount of $492,000.00. (Randy Orsby) 5. Resolution approving the lncrease and Renewal (Change No. 4) to Contract No. 12568 (formerly Contract No. C2569), Aerial Patrol Surve
Filing date: Not normalized. Collection: 2026-09-13T22:44:35.958564+00:00.
Tennessee · Shelby CountyUnreviewedMemphis City Council
ING, APPROV AL, AND ISSUANCE OF ZONING, LAND USE, BUILDING, AND OTHER ASSOCIATED INFRASTRUCTURE PERMITS FOR DATA CENTER DEVELOPMENTS WITHIN THE CITY OF MEMPHIS WHEREAS, pursuant to Tennessee Code Annotated § 13- 7-201, t he Memphis City Council possesses the authority to regulate land use , zoning, and development to protect the public health,
Filing date: Not normalized. Collection: 2026-09-13T22:40:31.440157+00:00.
Tennessee · Shelby CountyUnreviewedMemphis City Council
ELATED PURPOSES WHEREAS, Memphis seeks to become a preferred location for high- value digital and strategic large-load investment by offering faster certainty, prepared infrastructure, and a durable public bargain rather than either unregulated first-come access or a blanket closure; WHEREAS, the City already has agencies responsible for land
Filing date: Not normalized. Collection: 2026-09-13T22:40:32.560016+00:00.
Mississippi · State / regional scopeUnreviewedMississippi Public Service Commission
CKSON MISSISSIPPI, TUESDAY, SEPTEMBER 1, 2026 AT 10:00 A.M. CONTINUED ENERGY 2017-UA-79 SOUTHERN CROSS TRANSMISSION LLC INTERVENOR Filing Date: 4/25/17 IN RE: PETITION BY SOUTHERN CROSS TRANSMISSION LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY FOR THE PROPOSED SOUTHERN CROSS TRANSMISSION PROJECT 2019-UN-1 C
Filing date: Not normalized. Collection: 2026-09-13T22:40:31.043810+00:00.
Mississippi · State / regional scopeUnreviewedMississippi Public Service Commission
CKSON MISSISSIPPI, TUESDAY, SEPTEMBER 1, 2026 AT 10:00 A.M. CONTINUED ENERGY 2017-UA-79 SOUTHERN CROSS TRANSMISSION LLC INTERVENOR Filing Date: 4/25/17 IN RE: PETITION BY SOUTHERN CROSS TRANSMISSION LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY FOR THE PROPOSED SOUTHERN CROSS TRANSMISSION PROJECT 2019-UN-1 C
Filing date: Not normalized. Collection: 2026-09-13T22:40:32.053404+00:00.
Mississippi · State / regional scopeUnreviewedMississippi Public Service Commission
G, JACKSON MISSISSIPPI, TUESDAY, JULY 7, 2026 AT 10:00 A.M. CONTINUED ENERGY 2017-UA-79 SOUTHERN CROSS TRANSMISSION LLC INTERVENOR Filing Date: 4/25/17 IN RE: PETITION BY SOUTHERN CROSS TRANSMISSION LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY FOR THE PROPOSED SOUTHERN CROSS TRANSMISSION PROJECT 2019-UN-1 C
Filing date: Not normalized. Collection: 2026-09-13T22:40:33.099952+00:00.
Mississippi · State / regional scopeUnreviewedMississippi Public Service Commission
JACKSON MISSISSIPPI, TUESDAY, AUGUST 4, 2026 AT 10:00 A.M. CONTINUED ENERGY 2017-UA-79 SOUTHERN CROSS TRANSMISSION LLC INTERVENOR Filing Date: 4/25/17 IN RE: PETITION BY SOUTHERN CROSS TRANSMISSION LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY FOR THE PROPOSED SOUTHERN CROSS TRANSMISSION PROJECT 2019-UN-1 CIT
Filing date: Not normalized. Collection: 2026-09-13T22:40:33.927546+00:00.
Alabama · State / regional scopeUnreviewedAlabama Public Service Commission
6 2 MUNICIPAL 10 8 1 6 14 MASTER METER 2 LIQUID PROPANE (LP) LIQUIFIED NATURAL GAS /LNG) INTRASTATE 1 TRANSMISSION 3 2 3 GAS GATHERING 1 1 1 OFFSHORE GAS ~ ..-l "' ~~ ~~ @~ Cl -..-l REFINED PETROLEUM PRODUCTS 2 CRUDE OIL 3 HVL FLAMMABLE/ TOXIC CARBON DIOXIDE BIOFUEL TOTALS 14 15 1 0 0 0 0 9 27 0 66 Enforcement Actions From t
Filing date: Not normalized. Collection: 2026-09-13T22:44:40.468848+00:00.
Louisiana · Richland ParishUnreviewedLPSC — U-37425
Filing date: 2026-08-31. Collection: 2026-09-13T22:44:33.480139+00:00.
Louisiana · Richland ParishUnreviewedLPSC — U-37425
Public Redacted Version of Laidley Generation and Transmission Project Quarterly Monitoring Report for 2026 for Entergy Louisiana, LLC (Confidential Version Filed Under Seal)
Filing date: 2026-08-17. Collection: 2026-09-13T22:44:33.480237+00:00.